
01 May Construction Law Review
Construction Law Review – April
Please refer below to our Construction Law Review, selected from AR Conolly’s Daily Bulletins covering Insurance, Banking, Construction & Government.
Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq); Ostwald Bros Pty Ltd (in liq) v Seymour Whyte Constructions Pty Ltd [2018] NSWSC 412
Supreme Court of New South Wales
Stevenson J
Contract – security of payments – corporations – Seymour Whyte Constructions Pty Ltd (Seymour White) as contractor entered contract with Ostwald Bros Pty Ltd (now in liquidation) (Ostwald) as subcontractor to perform works – Seymour Whyte terminated contract under clause providing for ’termination without cause’ – Ostwald had earlier served payment claim on Seymour Whyte under Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) – Seymour Whyte did not pay Ostwald any of scheduled amount – Ostwald made adjudication application – adjudicator determined amount due by Seymour Whyte to Oswald – Seymour White contended determination was void as adjudication application was not made in time specified in s17 of the Act – held: Court satisfied that contract should rectified as Ostwald contended by deletion of certain special conditions – Ostwald’s adjudication application was in time – determination valid – any judgment obtained by Ostwald to be stayed until procedure in s553C Corporations Act 2001 (Cth) finalised.
View Decision
Supreme Court of New South Wales
Stevenson J
Contract – security of payments – corporations – Seymour Whyte Constructions Pty Ltd (Seymour White) as contractor entered contract with Ostwald Bros Pty Ltd (now in liquidation) (Ostwald) as subcontractor to perform works – Seymour Whyte terminated contract under clause providing for ’termination without cause’ – Ostwald had earlier served payment claim on Seymour Whyte under Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) – Seymour Whyte did not pay Ostwald any of scheduled amount – Ostwald made adjudication application – adjudicator determined amount due by Seymour Whyte to Oswald – Seymour White contended determination was void as adjudication application was not made in time specified in s17 of the Act – held: Court satisfied that contract should rectified as Ostwald contended by deletion of certain special conditions – Ostwald’s adjudication application was in time – determination valid – any judgment obtained by Ostwald to be stayed until procedure in s553C Corporations Act 2001 (Cth) finalised.
View Decision
Watkins Contracting Pty Ltd v Hyatt Ground Engineering Pty Ltd [2018] QSC 65
Supreme Court of Queensland
Brown J
Security of payments – applicant engaged first respondent to carry out works – parties entered construction contract but disputed its terms – applicant contended its contract terminated by principadue to incident, and that it terminated contract with respondent due to respondent’s breach of contract, or frustration on head contract’s termination – respondent made payment claim under Building and Construction Industry Payments Act 2004 (Qld) after contract allegedly terminated – adjudicator found in respondent’s favour – applicant contended adjudicator had no jurisdiction due to absence of available reference date , and that adjudicator erred by failing to consider its submissions – applicant also contended adjudicator denied it natural justice – held: adjudicator considered applicant’s submissions, did not deny applicant natural justice and did not commit jurisdictional error – application dismissed.
Watkins
Supreme Court of Queensland
Brown J
Security of payments – applicant engaged first respondent to carry out works – parties entered construction contract but disputed its terms – applicant contended its contract terminated by principadue to incident, and that it terminated contract with respondent due to respondent’s breach of contract, or frustration on head contract’s termination – respondent made payment claim under Building and Construction Industry Payments Act 2004 (Qld) after contract allegedly terminated – adjudicator found in respondent’s favour – applicant contended adjudicator had no jurisdiction due to absence of available reference date , and that adjudicator erred by failing to consider its submissions – applicant also contended adjudicator denied it natural justice – held: adjudicator considered applicant’s submissions, did not deny applicant natural justice and did not commit jurisdictional error – application dismissed.
Watkins
Laing O’Rourke Australia Construction Pty Ltd v Monford Group Pty Ltd [2018] NSWSC 491
Supreme Court of New South Wales
Stevenson J
Security of payments – – plaintiff was head contractor in relation to project – plaintiff engaged defendant subcontractor – defendant sought adjudication of payment claim under s17 Building and Construction Industry Security of Payments Act 1999 (NSW) – adjudicator found defendant entitled to payment of sum – dispute concerned variations claimed by defendant – adjudicator had found defendant entitled to part of sum claimed for variations – defendant had claimed 68 variations – plaintiff contended that adjudicator allowed defendant’s claim for 12 of the variations without considering the merits of the claim – principles in Pacific General Securities Ltd v Soliman & Sons (2006) 196 FLR 388 – held: adjudicator failed to consider merits of claim – adjudication quashed.
View Decision
Supreme Court of New South Wales
Stevenson J
Security of payments – – plaintiff was head contractor in relation to project – plaintiff engaged defendant subcontractor – defendant sought adjudication of payment claim under s17 Building and Construction Industry Security of Payments Act 1999 (NSW) – adjudicator found defendant entitled to payment of sum – dispute concerned variations claimed by defendant – adjudicator had found defendant entitled to part of sum claimed for variations – defendant had claimed 68 variations – plaintiff contended that adjudicator allowed defendant’s claim for 12 of the variations without considering the merits of the claim – principles in Pacific General Securities Ltd v Soliman & Sons (2006) 196 FLR 388 – held: adjudicator failed to consider merits of claim – adjudication quashed.
View Decision
A & A Martins Pty Limited v Liu [2018] ACTSC 102
Supreme Court of the Australian Capital Territory
McWilliam AsJ
Restitution – quantum meruit – plaintiff was construction company – defendants were owners of property – plaintiff contended it ‘substantially built a residential dwelling’ for defendants on property and it was not paid for most of the work, including materials supplied to defendants – defendants contended house substantially built by another corporate entity, a matter decided in Maples Winterview Pty Ltd v Liu and Li [2015] ACTSC 58 (Maples v Winterview) – defendants contended they did not pay for dwelling’s construction due to defects – defendants contended plaintiff was subcontractor which they had no obligation to pay – defendants also contended they became aware of plaintiff’s involvement only upon decision in Maples Winterview – ‘proper plaintiff’ – whether unconscionable for defendants to retain benefit without payment – whether ‘operable defence’ – remedy – held: defendants required to pay ‘a fair and reasonable sum’ for supplied goods and services – judgment for plaintiff.
A & A
Supreme Court of the Australian Capital Territory
McWilliam AsJ
Restitution – quantum meruit – plaintiff was construction company – defendants were owners of property – plaintiff contended it ‘substantially built a residential dwelling’ for defendants on property and it was not paid for most of the work, including materials supplied to defendants – defendants contended house substantially built by another corporate entity, a matter decided in Maples Winterview Pty Ltd v Liu and Li [2015] ACTSC 58 (Maples v Winterview) – defendants contended they did not pay for dwelling’s construction due to defects – defendants contended plaintiff was subcontractor which they had no obligation to pay – defendants also contended they became aware of plaintiff’s involvement only upon decision in Maples Winterview – ‘proper plaintiff’ – whether unconscionable for defendants to retain benefit without payment – whether ‘operable defence’ – remedy – held: defendants required to pay ‘a fair and reasonable sum’ for supplied goods and services – judgment for plaintiff.
A & A
Stay Informed – Connect with us on LinkedIn
Defect Remediation & Maintenance in Strata
Strata committees often ask why the presence of outstanding defects or maintenan...
27 February, 2025The Rising Risk of Tobacco Retailer Tenants for Strata and Property Owners
Earlier this year we wrote an article about high-risk tenants for strata and pro...
03 December, 2024Holiday Trading and After-Hours Information
CRM Brokers wishes you and your family a very Merry Christmas and we look forwar...
04 November, 2024The Importance of Police Reference Numbers for Claims
At CRM Brokers, we are committed to making our client’s claims experience ...
30 October, 2024